Private data center construction in the U.S. ran at a seasonally adjusted annual rate of roughly $96.5 billion in September, the highest level since 2014, according to U.S. Census Bureau data. At the same time, nearly half of the $80 billion in data center bonds raised this year carry junk ratings, according to a Forbes analysis . Construction is accelerating while data center financing is moving down the credit curve.

A quieter risk sits inside the structure of the deals themselves. The servers inside a data center, the building around them, the power plants that feed them and the contracts that pay for all of it run on very different timelines.

That mismatch surfaced repeatedly at “ Project 2050 : Exploring the Future of the Construction Industry,” a symposium convened Oct. 29-30 in Washington, D.C., by the National Academy of Construction, the American College of Construction Lawyers and the National Academy of Engineering. Speakers described three fault lines in data center financing: asset lives that don’t line up, long-term contracts that may outlast the companies that sign them and risk that lands with the parties least equipped to carry it.

Data Center Financing Runs On Mismatched Clocks

Douglas Mouton, founder of Mouton Advisory Services, who previously led procurement, engineering and construction for Microsoft and later worked on next-generation data center design at Meta, described a new class of AI cloud providers backed by “folks that have no money, good ideas, some software,” and funding packages from chipmakers. “It’s a credit guarantee for the life of the server, which is five years,” he said.

“The problem is, brick and mortar infrastructure depreciates over about 25 or 30 years,” Mouton continued. “So, if you’re underwriting this deal on the finance side, you’re like, ‘Wait a minute. What happens after five years?’” Investors who want silicon risk, he added, are typically not the same ones who want infrastructure risk.

Michael Kolodner, managing director, U.S. power and energy practice at Marsh, the insurance and professional services firm focused on risk, strategy, people and investments, addressed the power side of the equation. Components inside a data center generally need replacing every three to five years, he said, while the generation assets that power them are designed to last 30 to 40 years, and the power purchase agreements underpinning the capital typically run 20 to 30 years.

“What’s the probability that the economics of that revenue model continue to hold in year 7, year 15, year 20, year 25? We have no ability to predict that,” Kolodner said. “The conflict lies in long-term commitments built on shorter-term assumptions.”

Data Center Financing Depends On Contracts That Outlast Their Tenants

Kolodner said more than 95% of the data centers under construction today are financed by private capital, a sharp break from an energy system built largely by utilities. The credit risk tied to the contracts underpinning those investments “is without a doubt one of the biggest issues we have,” he said.

Traditional backstops such as parental guarantees, surety and letters of credit are limited. “There is a finite amount of that capital that can be used,” Kolodner said, warning that it is “going to be very, very expensive for a lot of communities when those defaults start happening.”

Not every contract carries the same weight. Arnab Datta, managing director of policy implementation at Employ America, a macroeconomic policy organization, and director of policy implementation at the Institute for Progress, a policy think tank, said he is skeptical of hyperscaler commitments to buy power from small modular reactors, given how much technological uncertainty remains. In contrast, he said Microsoft’s agreement to restart a retired nuclear unit “actually is meaningful because that project can get up and running,” and the contract pays above market.

That deal is a 20-year power purchase agreement with Constellation to restart the 835-megawatt Three Mile Island Unit 1, now called the Crane Clean Energy Center. Kolodner said one bilateral contract brought a plant previously deemed uneconomical – it had been retired for financial reasons in 2021 – “back from the dead.”

The reverse is also true. In September, Oracle sent a force majeure notice to Blue Owl Capital over Project Jupiter, a New Mexico data center, citing power and permitting delays. For business leaders, a signed contract is only as durable as the counterparty and the technology behind it.

Data Center Financing Pushes Risk Down The Chain

Mouton said about 70% of data center capacity in North America is delivered by third-party developers, many of them new to the market and short on capital. Debt providers respond with requirements for bonds, liquidated damages and other performance guarantees to manage their risk. “It drives right into the cost,” he said, estimating that the surety demanded by lenders is adding about 15 to 20% to project costs.

Mouton described “dogmatic flow downs of risk to the people who are least qualified to manage that risk,” often contractors and designers working on thin margins. “We just put the problem in a really bad place, and they don’t know what they have signed up for,” he said.

Kolodner made it clear that there is enough insurance to go around. “We’ve actually never had more risk capital available to deploy in support of financing assets ever,” he said. “The issue is how you actually connect that capacity to a new ecosystem of buyers,” particularly with new entrants that bring a significant amount of risk.

Building Resilience Into Data Center Financing

The last infrastructure boom offers a warning. During the renewable energy build-out, “we sacrificed resiliency in many cases to ensure that we could finance assets quickly,” Kolodner said. Investors with three- to five-year horizons got their returns, “and anything beyond that was really not their problem.” This time, he cautioned, potential stranded assets are “measured in billions of dollars, relative to the hundreds of millions that we saw in the last wave.”

The speakers pointed to practical disciplines. First, match capacity to real demand. Mouton recalled clients asking for hundreds of megawatts at once without knowing how they would fill them. “I think the biggest thing you have to do is talk your client off the ledge,” he said, and phase delivery to match actual demand instead. Second, plan for resilience across the full asset life cycle. Finally, put risk with the parties able to manage it.

For boards overseeing exposure to the build-out, whether as owners, lenders, builders or suppliers, those questions belong alongside the usual ones about demand and returns.

The AI build-out will be measured in gigawatts and dollars. Its durability will be measured in years, and specifically in whether the years on the contracts match the years on the assets. Aggressive data center financing that ignores that mismatch is a fragile endeavor that introduces risk to the communities that host them.